Reached the site at the break of dawn this morning to meet the Site Supervisor:
And when i reached the heavy machines were already operating there:
While talking to the SS a Port-a-loo was installed and driveway gravel was delivered:
By mid afternoon, half the site was leveled:
The pad needs to be at this level:
Thats all for today. By tomorrow the site should be completely cut and the Retaining Wall builder comes in on Wednesday.
The excavator man said that the neighbor already has a retaining wall on the right hand side of the block and i might not have to build one there myself .... lets see if the Retaining Wall builder gives me some discount as a result of this :)
Note: My neighbors, dunno which of the four ones that i have, had dumped some building and construction material on my site for which i had to pay an extra $600 to be taken to the tip (this was not included in the tender)